ISUZU 4JJ1 Euro 4 N Series Truck EGR Valve Removal and Installation Guide

When you need to replace new or used EGR valve,you need to remove and install EGR valve and cooler.Here comes the steps on how to remove and install EGR valve and cooler for ISUZU Euro 4 N series truck with 4JJ1 engine.

 

Related Contents:

ISUZU IDSS Diagnostic Tool

2023 2019 Isuzu G-IDSS Diagnostic Software Free Download (Troubleshooting Guide Included)

 

Procedures:

1.Drain the engine coolant.

2.Remove the AC generator.

3.Remove the engine cover.

4.Remove the fan guide bracket right.

5.Remove the exhaust adaptor and turbocharger water return pipe.

6.Remove the degassing hose.

7.Remove the degassing pipe.

8.Remove the heat protector.

9.Remove the EGR cooler.

Remove the(IN) and(OUT) rubber hoses of the water pipe, and remove the EGR cooler and the gasket.

10.Remove the EGR valve connector.

11.Remove the EGR valve.

 

Installation

If the procedures or methods for assembling the EGR device are mistaken, that can lead to cracks of pipe or gas leaks. Always follow the procedures.

1.Install the EGR valve.

Tightening torque:27 N-m(2.8kg-m/20 lb-ft)

2.Install the EGR valve connector.

3.Install the EGR cooler.

a.Attach the gasket and the EGR cooler, and temporarily tighten them in the order specified in the diagram.

b.Securely tighten them at the specified torque in the order as shown in the diagram.

Tightening torque: Nuts, Bolts(1)-(5)27 N·m(2.8kg-m/20 lb-ft)

4.Install the (IN) and (OUT) rubber hoses of the water pipe.

Install the rubber hose(IN) so that it does not interfere with the exhaust manifold heat protector.

5.Install the heat protector.

Tightening torque:25 N-m(2.5kg-m/18 lb-ft)

6.Install the degassing pipe.

a.Attach the degassing pipe, and temporarily tighten them in the order specified in the diagram.

b.Securely tighten them at the specified torque in the order as shown in the diagram.

Tightening torque Nuts, Bolts

(1),(3),(4),(5):10N-m(1.0kg-m/87 lb-in)

Nut(2):25N-m(2.5kg-m/18 lb-ft)

7.Install the exhaust adaptor and turbocharger water return pipe.

8.Install the fan guide bracket right.

9.Install the engine cover.

10.Install the AC generator.

11.Refill the engine coolant.

For more guide about ISUZU,please refer to:ISUZU Trouble Repair.

auto

Recent Posts

PCC1302 PowerCommand Low Coolant Level (Warning or Shutdown) Solution

PCC1302 PowerCommand Low Coolant Level (Warning or Shutdown) Solution   Related Contents: 2024 InPower V14.5…

14 hours ago

Volvo 2017 Engine Emissions ACM P054415 Exhaust Gas Sensor Error

The function identifies the exhaust temperature and indicates malfunction in the exhaust system. The evaluation…

4 days ago

How to Use MTU DiaSys Diagnostic Software to Connect MTU Engine

MTU DiaSys diagnostic software is professional on MTU engine diagnostics and programming.But seems that is…

6 days ago

Cummings ISX 12 and 15L EPA7 Engine Aftertreatment Injector Flow Test by JPRO

This instruction show you guide on how to use JPRO Diagnostic to do aftertreatment injector…

1 week ago

How to Setup Diagnostic Vendor Adapter for Hyster Yale PC Service Tool

There are several different diagnostic vendor adapter support Hyster and Yale forklift truck,here show you…

1 week ago

How to Use Deutz SerDia2010 SCR End Of Line Function

For correct use Deutz engine equipped with an SCR exhaust after treatment system is required.Here…

1 week ago