This instruction show you guide on how to use DMS-5 diagnostic software to calibrate swash plate angle for Doosan excavator.
Related Contents:
Doosan Data Monitoring System DMS-5 DMS-3 Free Download
Daios Doosan EPC Excavator Part Catalog 2017 Download & Installation
Procedures:
Swash Plate Angle Calibration
<Pump Swash plate angle sensor calibration concept>
1. In the case of VBO, the flow rate of the pump is controlled based on the swash plate angle sensor value, so the
sensor value must be measured at the maximum/minimum of the swash plate angle and calibration to the Software
reference value for accurate flow control.
2. That is, by measuring the swash plate angle sensor output(voltage) when the pump is at the maximum/minimum
position to calibrate the maximum/minimum swash plate angle value. 3.
3. For example, theoretically, the sensor output voltage at the maximum/minimum swash plates is at 4.5/0.5V, but if
the actual sensor value is 4.4/0.4V, it will be calibrated at 4.4V and the minimum at 0.4V.
<Caution>
1. The green light meaning of the displayed value is an indication that the tolerance for mounting the pump angle
sensor is within range, meaning no calibration is required. It is recommended that the measurements be calibration for
precise control.
2. That is, click ‘APPY’ after front pump calibration, and then click ‘APPLY’ again apply after rear pump calibration to save
the calibration value for each pump.
3. If the window displaying the value with red color, the pump is suspected to be defective so please contact Doosan regional service manager
Swash Plate Angle Calibration Setting before a test
Swash Plate Angle Calibration Process:
1.If it’s green – Click the Save button to save the calibration value.
2.If it’s red – Recalibration is performed 2-3 times, and if it continues to be red contact your
regional service manager.If it turns to green light after 2-3 times trials during recalibration, click the Save button to save
the calibration value
1.If it’s green – Click the Save button to save the calibration value.
2.If it’s red – Recalibration is performed 2-3 times, and if it continues to be red contact your
regional service manager.If it turns to green light after 2-3 times trials during recalibration, click the Save button to save the calibration value.
This instruction show you guide on how to solve Scania truck motion and inclination detector,…
This instruction show you guide on how to solve JCB excavator 140 C130C-13 spool brake solenoid…
Scania truck fault in the CAN communication with the chassis management system (CMS),this instruction show…
The water pumps used on all Phaser/1000 Series engines have been changed. The changes to…
Here is the simple instruction on how to solve Deutz engine EMR3 trouble code 48…
CAT ET 2025A Power Shift Pressure Test function checks whether that the proportional reducing valve is…