How to Use Deutz SerDia2010 SCR End Of Line Function

For correct use Deutz engine equipped with an SCR exhaust after treatment system is required.Here is the instruction show you guide on how to use Deutz SerDia2010 SCR End Of Line Function.

 

Related Contents:

2023 Deutz Serdia2010 v14.1.9.1 Diagnostic Software Free Download

Deutz Diagnostic Kit DECOM for Deutz Engine

 

 

The UseCase SCR-EOL is oppened from UseCase “SCR-Overview”
by pressing

 

 

Test is running as follows:
Step 1
– Start with click to

During whole test a stop is possible with activate

In order to run the test correct, following preferences have to be fulfilled:

Note:

No active error in ECU!
Engine speed is higher than 1500 rpm!
The used engine torque is more than 50% of the available torque!
If one of these three conditions is not met for more than 5 seconds,
the test is automatically aborted.

 

Step 2 – Trigger: temperatur prior oxi-catalyst >= 180°C
After step 1 is over, temerature is >180°C and all start conditions are met,a timer starts counting for 20 seconds (you can follow the timer, viewing the progress bar below the status window).

 

If the pressure of the SCR-pump will not reach more than 8,5 bar within the timer is running, the test will stop.
Deutz Communicator

 

 

Step 3 – Trigger: temperatur prior oxi-catalyst >= 250°C
After step 2 is finished successfully and temperature is more than 250°C ,a timer starts counting for 5 minutes (you can follow the timer, viewing the progress bar below the status window)

 

Test will stop, if AdBlue injection mass ist still lower than 10mg or NOX-value (prior catalyst) is higher than 10ppm within 5 minutes testing time.

Step 4 –Trigger: AdBlue amount >10mg, NOX-value (prior CAT) > 10ppm
For 10sec. an averaging of NOX values prior and after oxidation catalyst takes place.
The decrease of NOX concentration is measured meanwhile by collecting the min- and max-values of NOX concentration.
If, while averaging process takes place, the concentration gradient > 50ppm/10sec, averaging will stop and start again (in order to guarantee a
stationary measuring point).
After 5 repetitions without reaching a stationary operating point,the test is stopped completely.
Test is successful if converting rate is higher than 30%.
The test result is shown in an overview screen :

The result can be saved in a Log-file:

 

More topic for Deutz,please refer to Deutz Trouble Repair

auto

Recent Posts

JCB JS140 Excavator C130C-13 Spool Brake Solenoid Open Circuit Solution

This instruction show you guide on how to solve spool brake solenoid open circuit for…

1 day ago

Perkins 400A 400D Industrial Engine Crankshaft Rear Seal Remove and Install

This instruction show you guide on how to remove and install crankshaft rear seal for…

4 days ago

JPRO Diagnostic Software SCR Performance and System Test on Cummings

This instruction show you guide on how to use JPRO diagnostic to do SCR performance…

1 week ago

Yale ERP15-20VT G807 Forklift Truck Master Cylinder Removal and Disassemble Guide

Here is the instruction show you guide on how to remove and disassemble master cylinder…

1 week ago

How to Solve Deutz EMR3 71 / 2791 / EGRCD_SigNpl Error?

This instruction show you guide on how to solve Deutz EMR engine 71 / 2791 /…

2 weeks ago

How to Solve Allison 3000 & 4000 Gen5 P0731 Incorrect 2nd Gear Ratio?

Here is the instruction show you guide on how to repair P0731 incorrect 2nd gear ration…

2 weeks ago