Doosan heavy duty machine VBO calibration require you to do pump EPPR valve check,so here show you the steps.
Preparations:
Doosan Data Monitoring System DMS-5 DMS-3 Free Download
Pump EPPR valve check
*Calibration judgement
3.1. Measure the input & output current of the pump EPPR valve in certain condition
Ex. DX350LC-7, Normal outputs of pump EPPR valve (Please refer the shop manual to check the exact value
on each model)
3.2. Check the physical condition of the EPPR valve
3.2.1. Assembly condition
3.2.2. External damage
3.2.3. Short circuit
Ex. DX350LC-7(Please refer the shop manual to check the exact value on each model)
3.3. Measure the resistance of the EPPR valve
3.3.1. Measure the resistance of the valve coil: If the measurement is infinite, this indicates an
open circuit of the coil in the valve.
3.3.2. Measure the resistance of the valve coil: If the measurement is 0Ω, this indicates a short
circuit of the coil in the valve.
More topics for Doosan,please refer to:Doosan Trouble Repair
This instruction show you guide on how to solve Scania truck motion and inclination detector,…
This instruction show you guide on how to solve JCB excavator 140 C130C-13 spool brake solenoid…
Scania truck fault in the CAN communication with the chassis management system (CMS),this instruction show…
The water pumps used on all Phaser/1000 Series engines have been changed. The changes to…
Here is the simple instruction on how to solve Deutz engine EMR3 trouble code 48…
CAT ET 2025A Power Shift Pressure Test function checks whether that the proportional reducing valve is…